Activity slack or float of any event on a PERT/CPM chart is represented by

A Latest start time of succeeding event earliest finish time of preceding event activity time
B Latest start time of the event earliest start time of the event
C Latest finish time of event earliest finish time of the event
D Anyone of the above

Correct Answer: Anyone of the above

Activity slack or float of any event on a PERT/CPM chart is represented by
- Latest start time of succeeding event earliest finish time of preceding event activity time
- Latest start time of the event earliest start time of the event
- Latest finish time of event earliest finish time of the event

Related Questions

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
(i) Why do we remember May Day? (ii) What significant changes happened due to that event? (iii) How did the event happen? (iv) What can be done in present day as a result of that event ? (v) Mention the moral of that event.
Slack of various events on the critical path in PERT/CPM chart
Slack is the calculated time span within which the event must occur:
When slack of an activity is negative
When slack of an activity is positive
Total float for any activity is defined as the difference between