Activity slack or float of any event on a PERT/CPM chart is represented by
Activity slack or float of any event on a PERT/CPM chart is represented by Correct Answer Anyone of the above
Activity slack or float of any event on a PERT/CPM chart is represented by- Latest start time of succeeding event earliest finish time of preceding event activity time
- Latest start time of the event earliest start time of the event
- Latest finish time of event earliest finish time of the event