Total float for any activity is defined as the difference between
A
Its latest finish time and earliest start time for its successor activity
B
Its latest start time and earliest start time
C
Its latest start time and earliest finish time
D
Its earliest finish time and earliest start time for its successor activity
Correct Answer: Its latest start time and earliest start time