Free float for any activity is defined as the difference between

A its earliest finish time and earliest start time for its successor activity
B its latest start time and earliest start time
C its latest finish time and earliest start time for its successor activity
D its earliest finish time and latest start time for its successor activity

Correct Answer: its earliest finish time and earliest start time for its successor activity