When slack of an activity is negative

A It represents a situation where extra resources are available and the completion of project is not delayed
B It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C The activity is critical and any delay in its performance will delay the completion of whole project
D All of the above

Correct Answer: It represents that a programme falls behind schedule and additional resources are required to complete the project in time

When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time