When slack of an activity is negative
A
It represents a situation where extra resources are available and the completion of project is not delayed
B
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C
The activity is critical and any delay in its performance will delay the completion of whole project
D
All of the above
Correct Answer: It represents that a programme falls behind schedule and additional resources are required to complete the project in time
When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time