When slack of an activity is positive

A It represents a situation where extra resources are available and the completion of project is not delayed
B It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C The activity is critical and any delay in its performance will delay the completion of whole project
D Any one of the above

Correct Answer: It represents a situation where extra resources are available and the completion of project is not delayed

When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.
When slack of an activity is negative - it represents that a program falls behind schedule and additional resources are required to complete the project in time.
When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.

Related Questions

Activity slack or float of any event on a PERT/CPM chart is represented by
When slack of an activity is negative
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
Positive slack on a PERT indicates that project is
Slack is the calculated time span within which the event must occur:
Slack time refers to
In a band and block brake, the ratio of tensions on tight side and slack side of the band is (where $$\mu $$ = Coefficient of friction between the blocks and the drum, $$\theta $$ = Semi-angle of each block subtending at the center of drum and n = Number of blocks)

Next steps