When slack of an activity is positive
A
It represents a situation where extra resources are available and the completion of project is not delayed
B
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C
The activity is critical and any delay in its performance will delay the completion of whole project
D
Any one of the above
Correct Answer: It represents a situation where extra resources are available and the completion of project is not delayed
When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.When slack of an activity is negative - it represents that a program falls behind schedule and additional resources are required to complete the project in time.
When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.