Positive slack on a PERT indicates that project is
A
Ahead of schedule
B
Beyond schedule
C
As per schedule
D
On critical path
Correct Answer: Ahead of schedule
A positive slack indicates the amount of time that the task can be delayed without delaying the project finish date.