If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
A
Latest start time earliest start time
B
Latest finish time earliest finish time (EFT)
C
TLEFT
D
All of the above
Correct Answer: All of the above
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to- Latest start time earliest start time
- Latest finish time earliest finish time (EFT)
- TLEFT