If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A Latest start time earliest start time
B Latest finish time earliest finish time (EFT)
C TLEFT
D All of the above

Correct Answer: All of the above

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
- Latest start time earliest start time
- Latest finish time earliest finish time (EFT)
- TLEFT

Related Questions

Activity slack or float of any event on a PERT/CPM chart is represented by
(i) Why do we remember May Day? (ii) What significant changes happened due to that event? (iii) How did the event happen? (iv) What can be done in present day as a result of that event ? (v) Mention the moral of that event.
Slack is the calculated time span within which the event must occur:
When slack of an activity is negative
When slack of an activity is positive
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Slack time refers to

Next steps