If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

A $$\frac{{{\text{a}} + {\text{m}} + {\text{b}}}}{6}$$
B $$\frac{{{\text{a}} + 2{\text{m}} + {\text{b}}}}{6}$$
C $$\frac{{{\text{a}} + 4{\text{m}} + {\text{b}}}}{6}$$
D $$\frac{{{\text{a}} + 5{\text{m}} + {\text{b}}}}{6}$$

Correct Answer: $$\frac{{{\text{a}} + 4{\text{m}} + {\text{b}}}}{6}$$