Pessimistic time is

Pessimistic time is Correct Answer The maximum time which an activity might require

Pessimistic time is a concept used in the program evaluation and review technique (PERT). It represents the longest estimated time period within which a task is likely to be completed, and is used in project planning.

Related Questions

In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be