The total blow required for the second and third 15 cm of penetration in standard penetration test is taken as ____________
The total blow required for the second and third 15 cm of penetration in standard penetration test is taken as ____________ Correct Answer Seating drive
In standard penetration test, the first 15 cm of drive may be considered to be a seating drive. The total blows required for the second and third 15 cm of penetration is termed as the penetration resistance N.