A and B can do a job in 5 days, B and C can do the same job in 6 days and C and A can do the same job in 7.5 days. A, B, and C together will complete the same job in how many days?
A and B can do a job in 5 days, B and C can do the same job in 6 days and C and A can do the same job in 7.5 days. A, B, and C together will complete the same job in how many days? Correct Answer 4
Given
A and B can do job in 5 days.
B and C can do job in 6 days.
C and A can do job in 7.5 days.
Formula used
Total work = Efficiency × Time taken
Calculation
Let total work be 30 units (LCM of 5, 6 and 7.5).
Now, efficiency of A + B = 30/5 = 6 unit/day ---- (1)
And, efficiency of B + C = 30/6 = 5 units/day ---- (2)
And, efficiency of A + C = 30/7.5 = 4 units/day ---- (3)
Adding 1, 2 and 3, we get
2(A + B + C) = 15 units/day
⇒ A + B + C = 15/2 = 7.5 units/day
∴ Time taken by A, B and C to complete the work = 30/7.5 = 4 days