P and Q together can complete a work in 105 days. Q and R together can complete the same work in 90 days, P and R together can complete the same work in 126 days. In how many days P, Q and R together can complete the same work?
P and Q together can complete a work in 105 days. Q and R together can complete the same work in 90 days, P and R together can complete the same work in 126 days. In how many days P, Q and R together can complete the same work? Correct Answer 70 days
Formula used:
Efficiency = 1/Number of days required to complete work
Calculation:
Work done by P and Q in 1 day = 1/105
Work done by Q and R in 1 day = 1/90
Work done by R and P in 1 day = 1/126
Adding all of them together
⇒ 2 × (R + P + Q) = 1/105 + 1/90 + 1/126 = 1/35
⇒ R + P + Q = 1/70
∴ R, P and Q can complete the work in 70 days