A man and a boy together can complete a job in 81 days. Two men and three boys together can complete the same job in 36 days. In how many days can four men together complete the same job?

A 21
B 27
C 30
D 36

Correct Answer: 27

Man = M , Boy = B1M + 1B = 1/8181M + 81B = 1 work2M + 3B = 1/3672M + 108B = 1 work81M + 81B = 72M + 81B9M = 27B 1M = 3B4M = 12B12B = 4/12 x 81 Days4M = 27 Days 