A and B, working together, can be complete a work in 16 days, C and A together can complete in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work?
A and B, working together, can be complete a work in 16 days, C and A together can complete in 32 days, B and C together can complete it in 24 days. They worked together for 12 days. In how many days will C alone complete the remaining work? Correct Answer 36
Let the total work be 96.
(Lcm of 16, 32 and 24 is 96)
Efficiency of (A + B) = 6
Efficiency of (B + C) = 4
Efficiency of (C + A) = 3
Efficiency of 2(A + B + C) = 13
Efficiency of (A + B + C) = 6.5
Work of 12 days = 6.5 × 12 = 78
Remaining work = 96 - 78 = 18
Efficiency of C = 6.5 - 6 = 0.5
Days to complete remaining work = 18/0.5 = 36 days