In critical path method, when a particular task is performed, it is called:
In critical path method, when a particular task is performed, it is called: Correct Answer Activity
An activity is defined as the actual performance of a task which consumes time and requires resources (such as labor, materials, space, machinery). It can be understood as representing the time, effort, and resources required to move from one event to another. An activity cannot be performed until the predecessor event has occurred.