Slack represents the difference between the

A Latest allowable time and the normal expected time
B Latest allowable time and the earliest expected time
C Proposed allowable time and the earliest expected time
D Normal allowable time and the latest expected time

Correct Answer: Latest allowable time and the earliest expected time

Slack represents the difference between the Latest allowable time and the earliest expected time

Related Questions

In a band and block brake, the ratio of tensions on tight side and slack side of the band is (where $$\mu $$ = Coefficient of friction between the blocks and the drum, $$\theta $$ = Semi-angle of each block subtending at the center of drum and n = Number of blocks)
In a band and block brake, the ratio of tensions on the tight and slack sides of band is given by (where $$\mu $$ = Coefficient of friction between the blocks and the drum, $$\theta $$ = Semi-angle of each block subtending at the centre of drum and n = Number of blocks)
Slack is the calculated time span within which the event must occur:
Slack time refers to
Slack of various events on the critical path in PERT/CPM chart
Activity slack or float of any event on a PERT/CPM chart is represented by
When slack of an activity is negative

Next steps