After receipt of an application for establishment of a factory as required under the Factories Act, 1948, in how many days the Site Appraisal Committee is required to submit its report to the State Government?
After receipt of an application for establishment of a factory as required under the Factories Act, 1948, in how many days the Site Appraisal Committee is required to submit its report to the State Government? Correct Answer 90 days