If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then Correct Answer expected time of both activities A and B are same

Related Questions

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)