The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time) Correct Answer $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + 4{{\text{t}}_{\text{n}}}}}{6}$$

The probabilistic time is given by $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + 4{{\text{t}}_{\text{n}}}}}{6}$$
Where to = Optimistic time, tp = Pessimistic time and tn = Most likely time.

Related Questions

The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression
If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given as