A and B can finish a work in 2.4 days. If the number of days for which they work increases by 2 days each for A and B then time taken by them together to finish the work is 24/7 days. Find the time taken by them to complete the work together, If the number of days for which they work increases by 4 days each?
A and B can finish a work in 2.4 days. If the number of days for which they work increases by 2 days each for A and B then time taken by them together to finish the work is 24/7 days. Find the time taken by them to complete the work together, If the number of days for which they work increases by 4 days each? Correct Answer 40/9
Given:
A and B can finish a work in 2.4 days.
Formula used:
Time taken by A and B to together finish a work which they alone finish in ‘a’ and ‘b’ days respectively is a × b/(a + b)
Calculation:
Let ‘A’ is the work done by A in a day and ‘B’ is the work done by B in a day
⇒ Let total work = 24 units, multiple of 2.4 (any value as it will not affect the answer)
Work done by both in a day = 24/2.4 = 10 units
⇒ A + B = 10
Let A = 4 units and B = 6 units if we take reverse then also it will not affect the answer
So, A alone can complete = 24/4 = 6 days and for B = 24/6 = 4 days
If each of them takes 2 days more
⇒ A = 6 + 2 = 8 days and B = 6 days
Now, A = 24/8 = 3 units and B = 24/6 = 4 units
⇒ A + B = 4 + 3 = 7 units, Total time = 24/7 satisfies condition
Now, both takes 4 days more each
⇒ A can complete in 6 + 4 = 10 days
⇒ and B in 4 + 4 = 8 days
∴ Required time = 10 × 8/(10 + 8) = 80/18 = 40/9 days