A and B can finish a work in 2.4 days. If the number of days for which they work increases by 2 days each for A and B then time taken by them together to finish the work is 24/7 days. Find the time taken by them to complete the work together, If the number of days for which they work increases by 4 days each?

A and B can finish a work in 2.4 days. If the number of days for which they work increases by 2 days each for A and B then time taken by them together to finish the work is 24/7 days. Find the time taken by them to complete the work together, If the number of days for which they work increases by 4 days each? Correct Answer 40/9

Given:

A and B can finish a work in 2.4 days.

Formula used:

Time taken by A and B to together finish a work which they alone finish in ‘a’ and ‘b’ days respectively is a × b/(a + b)

Calculation:

Let ‘A’ is the work done by A in a day and ‘B’ is the work done by B in a day

⇒ Let total work = 24 units, multiple of 2.4 (any value as it will not affect the answer)

Work done by both in a day = 24/2.4 = 10 units

⇒ A + B = 10

Let A = 4 units and B = 6 units if we take reverse then also it will not affect the answer

So, A alone can complete = 24/4 = 6 days and for B = 24/6 = 4 days

If each of them takes 2 days more

⇒ A = 6 + 2 = 8 days and B = 6 days

Now, A = 24/8 = 3 units and B = 24/6 = 4 units

⇒ A + B = 4 + 3 = 7 units, Total time = 24/7 satisfies condition

Now, both takes 4 days more each

⇒ A can complete in 6 + 4 = 10 days

⇒ and B in 4 + 4 = 8 days

∴ Required time = 10 × 8/(10 + 8) = 80/18 = 40/9 days

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.