A and B can finish a work together in 30 days. B and C can finish the same work together in 24 days. A and C can finish the work together in 40 days. If all three work together, how long will it take them to complete the work?
A and B can finish a work together in 30 days. B and C can finish the same work together in 24 days. A and C can finish the work together in 40 days. If all three work together, how long will it take them to complete the work? Correct Answer 20 days
[ alt="F1 V.G Deepak 29.11.2019 D 9" src="//storage.googleapis.com/tb-img/production/19/11/F1_V.G_Deepak_29.11.2019_D%209.png" style="width: 255px; height: 121px;">
Efficiency of (A + B) (B + C) and (C + A) together = A + B + B + C + C + A = 4 + 5 + 3 = 12
2(A + B + C) = 12
A + B + C = 6
Time taken by (A + B + C) to complete the work = 120/6 = 20 days
Alternate Solution∶
Efficiency of A and B when they work together = 1/30
Efficiency of B and C when they work together = 1/24
Efficiency of A and C when they work together = 1/40
⇒ Efficiency of (A + B), (B + C) and (C + A) when they work together = 1/30 + 1/24 + 1/40
= (4 + 5 + 3)/120 = 12/120 = 1/10
∴ Efficiency of A, B and C when they work together = 1/2 × 1/10 = 1/20
Time taken by A, B and C to complete the work when they work together
= 1/(1/20) = 20 days.