4 views

1 Answers

The planning process takes 2.5 weeks, the permitting process takes 2 weeks, and the building process takes 12 weeks. Then, there's a chemical setup that takes approximately a week and a half to complete—this ensures that the pool's pH level matches the chlorine level.