Sunder, Ramu, and Chhotu can dig a well in 9, 18 and 36 days respectively. They all started digging together. Sunder worked continuously till well dug completely, Ramu leaves the work 3 days before its completion and Chhotu leaves the work 2 days before its completion. What is the time taken to dig the well?
Sunder, Ramu, and Chhotu can dig a well in 9, 18 and 36 days respectively. They all started digging together. Sunder worked continuously till well dug completely, Ramu leaves the work 3 days before its completion and Chhotu leaves the work 2 days before its completion. What is the time taken to dig the well? Correct Answer 44/7 days
Given
Sunder, Ramu, and Chhotu can dig a well respectively in = 9, 18 and 36 days
Formula used
Rate of Work = 1/Time Taken
Calculation
Let the well dug completely in days = x days
Work done by Sunder in 1 day = 1/9
Work done by Ramu in 1 day = 1/18
Work done by Chhotu in 1 day = 1/36
So According to question,
x/9 + (x-3)/18 + (x-2)/36 = 1
⇒ (4x + 2x - 6 + x - 2)/36 = 1
⇒ (7x - 8)36 = 1
⇒ 7x - 8 = 36
⇒ 7x = 36 + 8
⇒ x = 44/7
∴ Time taken to dig the well completely is 44/7 days.