A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed? Correct Answer 24 days

Let the work be completed in x days. C work for x days then A works for (x - 8) days and B works for (x - 12) days.According to the question,
$$\eqalign{ & {\frac{{ {x - 8} }}{{36}} + \frac{{ {x - 12} }}{{54}} + \frac{x}{{72}}} = 1 \cr & {\frac{{ {6x - 48 + 4x - 48 + 3x} }}{{216}}} = 1 \cr & 13x - 96 = 216 \cr & 13x = 216 + 96 = 312 \cr & x = \frac{{312}}{{13}} \cr & x = 24\,{\text{days}} \cr} $$

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.