C takes twice as long as B to complete a work. A takes three times as long as C to complete the same work. A, B and C start working together. A leaves 6 days before the completion of work and B leaves 3 days before the completion of work and C works for x days. If B alone can complete the same work in 16 days, then in how many days the work will be completed?
C takes twice as long as B to complete a work. A takes three times as long as C to complete the same work. A, B and C start working together. A leaves 6 days before the completion of work and B leaves 3 days before the completion of work and C works for x days. If B alone can complete the same work in 16 days, then in how many days the work will be completed? Correct Answer 12 <span style="color: rgb(37, 37, 37);">days</span>
Given:
Let time taken by C alone to complete the work be a days.
⇒ B alone can complete the work in = a/2 = 16
⇒ C alone can complete the work in = 32 days
⇒ A alone can complete the work in = 3a = 3 × 32 = 96 days
Calculation:
LCM of their work time = LCM(96, 16 and 32) = 96
⇒ A, B and C works for = 1 units per day, 6 units per day and 3 unites per day.
⇒ A + B + C = 1 + 6 + 3 = 10 units per day
⇒ B + C = 6 + 3 = 9 units per day
⇒ Work done in last 3 days = 3 × 3 = 9 units
⇒ Work done in last six days = 9 + 9 × 3 = 36 units
⇒ Remaining work after 6 days = 96 - 36 = 60 units
⇒ 60 units completed in = 60/10 = 6 days
⇒ Total days = 6 + 6 = 12 days
∴ Time required to complete work is 12 days.