P alone can complete the work in 12 days and Q alone can complete the work in 24 days. If P works alone for the first day and Q alone works for second day, after second day P and Q works together for next 5 days. After 7 days, R who has same work efficiency as Q, joins P and Q. In how many days, work will be completed?
P alone can complete the work in 12 days and Q alone can complete the work in 24 days. If P works alone for the first day and Q alone works for second day, after second day P and Q works together for next 5 days. After 7 days, R who has same work efficiency as Q, joins P and Q. In how many days, work will be completed? Correct Answer 8.5 days
Given,
P's 1 day’s work = 1/12
Q's 1 day's work = 1/24
R's 1 day's work = 1/24
(P + Q)’s 1 day's work = 1/12 + 1/24 = 1/8
(P + Q + R)’s 1 day's work = 1/12 + 1/24 + 1/24 = 1/6
First two days’ work = 1/12 + 1/24 = 1/8
(P + Q)’s 5 days’ work = 5/8
Total work completed by P and Q in 7 days =
= 5/8 + 1/8
= 3/4
Remaining work = 1 – 3/4 = 1/4
Number of days taken by P, Q and R to complete the work =
= 1/4 × 6
= 3/2
Total number of days = 7 + 1.5 = 8.5 days