A and B together can do a piece of work in 60 days. B and C together can do the work in 40 days. A starts the work and works on it for 16 days then leaves. Then B takes up, works for 28 days, and leaves. Finally, C finishes the remaining work in 38 days. In how many days can B complete the entire work alone?
A and B together can do a piece of work in 60 days. B and C together can do the work in 40 days. A starts the work and works on it for 16 days then leaves. Then B takes up, works for 28 days, and leaves. Finally, C finishes the remaining work in 38 days. In how many days can B complete the entire work alone? Correct Answer 120 days
Given:
A and B together can do a piece of work = 60 days
B and C together can do a piece of work = 40 days
Concept Used:
Efficiency = Time taken × Work done
Calculation:
Let the total work be 120 (LCM of 60 ,40)
Let the efficiency of C be x
According to the question, we have
The efficiency of (A + B) = 120/60 ⇒ 2
The efficiency of (B + C) = 120/40 ⇒ 3
Now, A work for 16 days and B work for 28 days
Let assume A and B work together be 16 days
Let assume B and C work together be 12 days
Let assume C work alone be 26 days
According to the question,
(A + B) × 16 + (B + C) × 12 + C × 26 = 120
⇒ 2 × 16 + 3 × 12 + x × 26 = 120
⇒ 32 + 36 + 26x = 120
⇒ 26x = 120 - 68
⇒ 26x = 52
⇒ x = 2
The efficiency of B = The efficiency of (B + C) - The efficiency of C
The efficiency of B = 3 - 2 ⇒ 1
Now,
B can complete the entire work alone = (Total work)/(Efficiency of B)
⇒ 120/1 ⇒ 120 days
∴ The B can complete the entire work alone in 120 days.