6 men can complete a work in 64 days. 24 women can complete the same work in 32 days. 16 men and 24 women together worked for 12 days, after which 8 men and 8 women were dropped. In how many days the work will be completed?

6 men can complete a work in 64 days. 24 women can complete the same work in 32 days. 16 men and 24 women together worked for 12 days, after which 8 men and 8 women were dropped. In how many days the work will be completed? Correct Answer 15

Given:

Total time taken by 6 men to complete the work = 64 days

Total time taken by 24 women to complete the work = 32 days

Formula used:

Total work = Total efficiency × Total time

Calculation:

Let, M = Man and W = Woman

So, 6M × 64 = 24W × 32

⇒ M/W = 2/1

∴ A man can do in a day = 2 work

∴ A woman can do in a day = 1 work

Total work = (24 × 1) × 32 = 768

The total work by 16 men and 24 women for 12 days =  × 12

= 12 (32 + 24)

The total work done by 8 men and 16 women for one day = (8 × 2) + (16 × 1) = 32

Suppose, the total time is taken by  8 men and 16 women = x

Then, 12 (32 + 24) + 32x = 768

⇒ (12 × 56) + 32x = 768

⇒ 32x = 768 - 672

⇒ 32x = 96

⇒ x = 96/32 = 3

∴ Total required time = 12 + 3 = 15 days

∴ The work will be completed in 15 days.

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.