The question below is followed by two statements I, II and III. You have to determine whether the data given is sufficient for answering the question. You should use the data and your knowledge of mathematics to choose the best possible answer. How many workers are required for completing the construction work in 10 days? I. 40% of the work can be completed by 8 workers in 12 days II. 25 workers can complete the work in 12 days III. one fifth of the work can be completed by 12 workers in 15 days
The question below is followed by two statements I, II and III. You have to determine whether the data given is sufficient for answering the question. You should use the data and your knowledge of mathematics to choose the best possible answer. How many workers are required for completing the construction work in 10 days? I. 40% of the work can be completed by 8 workers in 12 days II. 25 workers can complete the work in 12 days III. one fifth of the work can be completed by 12 workers in 15 days Correct Answer Any of three Statements is sufficient
Statement I:
8 × 12 = 10 × number of workers
Number of workers = 24
Statement I alone is sufficient
Statement II:
12 × 25 = 10 × number of workers
Number of workers = (12 × 25)/10
Statement II alone is sufficient
Statement III:
(12 × 15) 5 = 10 × number of workers
Statement III alone is sufficient