Munna is twice efficient as Cheeku and Cheeku can do a piece of work in 40 days. Cheeku started the work and after a few days Munna joined him. They completed the work in 32 days. From the starting, for how many days they worked together?
Munna is twice efficient as Cheeku and Cheeku can do a piece of work in 40 days. Cheeku started the work and after a few days Munna joined him. They completed the work in 32 days. From the starting, for how many days they worked together? Correct Answer 4 days
GIVEN:
Work efficiency of Munna = 2 × Work efficiency of Cheeku
Cheeku can do a piece of work in 40 days
They completed the work in 32 days
CALCULATION:
Munna Cheeku
Efficiency 1 : 2
Cheeku’s one day work = 1/40
Munna’s one day work = 1/20
(Munna + Cheeku) one day work = 1/40 + 1/20 = (1+2)/40 = 3/40
Now, let us assume Cheeku joined Munna after (32 – x) days then,
(32 – x)/40 + (x × 3)/40 = 1
⇒ (32 – x + 3x)/40 = 1
⇒ 32 + 2x = 40
⇒ x = 4
∴ They worked for 4 days together