A, B, and C can do a piece of work in 12, 15, and 20 days respectively. A can do the work for 5 days after that B joined A and A works with his half efficiency. They both worked for 2 days together and after that C joined them and B works with 1 / 4 of his efficiency. They all worked together for 2 days and after that C left and A and B are working their normal efficiency. Then find In how many days A and B can complete the remaining work.
A, B, and C can do a piece of work in 12, 15, and 20 days respectively. A can do the work for 5 days after that B joined A and A works with his half efficiency. They both worked for 2 days together and after that C joined them and B works with 1 / 4 of his efficiency. They all worked together for 2 days and after that C left and A and B are working their normal efficiency. Then find In how many days A and B can complete the remaining work. Correct Answer 1 day
Given:
A can do a piece of work = 12 days
B can do a piece of work = 15 days
C can do a piece of work = 20 days
Concept used:
Total work = LCM
Work done in unit value of time is known as efficiency
Formula used:
Efficiency = total work / total days
Calculations:
Let the total work be x
∴ Efficiency of A = total work / total days = x / 12
∴ Efficiency of B = total work / total days = x / 15
∴ Efficiency of C = total work / total days = x / 20
∵ A can do the work for 5 days
∴ Work done by A = (x / 12) × 5 = 5x / 12
∵ After 5 days B joined A and A works with half of his efficiency for next 2 days
∴ Work done by A and B in one day = (x / 24) + (x / 15) = 13x / 120
∴ Work done by A and B in two days = 2 × (13x / 120) = 13x / 60
∵ After 5 days C joined A and B, B works with 1 / 4 of his efficiency for next 2 days
∴ Work done by A, B and C in one day = (x / 24) + (x / 60) + (x / 20) = 13x / 120
∴ Work done by A, B and C in two days = 2 × (13x / 120) = 13x / 60
Total work completed in 9 days = (5x / 12) + (13x / 60) + (13x / 60) = 51x / 60 = 17x / 20
∴ The remaining work = x – (17x / 20) = 3x / 20
∵ For remaining work C left and A and B work with their normal efficiency
∴ Work done by A and B in one day = (x / 12) + (x / 15) = 9x / 60 = 3x / 20
∴ Remaining work done by A and B = remaining work / efficiency
⇒ (3x / 20) ÷ (3x / 20) = 1 day
Alternate method:
Total work = LCM = 60
∴ Efficiency of A = total work / total days = 60 / 12 = 5
∴ Efficiency of B = total work / total days = 60 / 15 = 4
∴ Efficiency of C = total work / total days = 60 / 20 = 3
∵ A can do the work for 5 days
∴ Work done by A = 5 × 5 =25
∵ After 5 days B joined A and A works with half of his efficiency for next 2 days
∴ Work done by A and B in one day = (5 / 2) + 4 = 13 / 2
∴ Work done by A and B in two days = 2 × (13 / 2) = 13
∵ After 5 days C joined A and B, B works with 1 / 4 of his efficiency for next 2 days
∴ Work done by A, B and C in one day = (5 / 2) + 1 + 3 = 13 / 2
∴ Work done by A, B and C in two days = 2 × (13 / 2) = 13
Total work completed in 9 days = 25 + 13 + 13 = 51
∴ The remaining work = 60 – 51 = 9
∵ For remaining work C left and A and B work with their normal efficiency
∴ Work done by A and B in one day = 5 + 4 = 9
∴ Remaining work done by A and B = remaining work / efficiency
⇒ 9 / 9 = 1 day