A, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together every third day. In how many days will the work be completed?
A, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together every third day. In how many days will the work be completed? Correct Answer 23
[ alt="F1 V.K Deepak 15.02.2020 D7" src="//storage.googleapis.com/tb-img/production/20/02/F1_V.K_Deepak_15.02.2020_D7.png" style="width: 206px; height: 160px;">
Total work = 90
Work done by A, B and C in 3 days = 3A + B + C = 3 × 3 + 2 + 1 = 12
Work done by A, B and C in 21 days = 12 × 7 = 84
Remaining work = 90 – 84 = 6
A will complete 6 unit work in 6/3 = 2 days
Total days = 21 + 2 = 23