A and B can complete a task in 18 days. However, A had to leave a few days before the task was completed and hence it took 27 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave?
A and B can complete a task in 18 days. However, A had to leave a few days before the task was completed and hence it took 27 days in all to complete the task. If A alone could complete the work in 21 days, how many days before the work getting over did A leave? Correct Answer 10.5