Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.

Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha. Correct Answer 60 days

Suppose, Asha takes x days to complete the task alone
while Sudha takes y days to complete it alone
Since Sudha is more efficient than Asha, we have x > y
$$\eqalign{ & {\text{Asha's 1 day's work}} = \frac{1}{x} \cr & {\text{Sudha's 1 day's work}} = \frac{1}{y} \cr & \left( {{\text{Asha}} + {\text{Sudha}}} \right){\text{'s 1 day's work}} \cr & = \frac{1}{x} + \frac{1}{y} \cr & = \frac{{x + y}}{{xy}} \cr} $$
If Asha and Sudha each does half of the work alone, time taken
$$\eqalign{ & = \left( {\frac{x}{2} + \frac{y}{2}} \right){\text{ days }} \cr & = \left( {\frac{{x + y}}{2}} \right){\text{ days}}{\text{.}} \cr & \therefore \frac{{x + y}}{2} = 45 \cr & \Rightarrow x + y = 90 \cr & {\text{From (i) and (ii), }} \cr & {\text{We have}}:\frac{{xy}}{{20}} = 90{\text{ or }}xy = 1800 \cr & {\text{Now, }}xy = 1800{\text{ and }}x + y = 90 \cr & \Rightarrow x = 60,{\text{ }}y = 30{\text{ }}\left{\text{ }} \cr} $$
Hence, Asha alone will take 60 days to complete the task.

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.