A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?
A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself? Correct Answer 20
Given,
(A + B)’s 1 day’s work = 1/12
⇒ 1/A + 1/B = 1/12
Given,
⇒ (A/2) + (B/2) = 25
⇒ A + B = 50
Solving,
⇒ 1/ (50 – B) + 1/B = 1/12
⇒ B2 – 50B + 600 = 0
⇒ B2 – 30B – 20B + 600 = 0
⇒ B(B – 30) – 20(B – 60) = 0
⇒ B = 30 or B = 20
If B = 30 Then A = 20
If B = 20 Then A = 30
But B is more efficient than A,
∴ B takes 20 days to complete the work.
মোঃ আরিফুল ইসলাম
Feb 20, 2025