Three boys Alpha, Beta and Gama planned to make a sports car. Alpha and Beta can finish the task in 18 days; Beta and Gama can do it in 24 days while Gama and Alpha can finish it in 36 days. In how many days will each one of them finish it?

Three boys Alpha, Beta and Gama planned to make a sports car. Alpha and Beta can finish the task in 18 days; Beta and Gama can do it in 24 days while Gama and Alpha can finish it in 36 days. In how many days will each one of them finish it? Correct Answer Alpha = 48 days; Beta = 144/5 days; Gama = 144 days

Given:

Alpha and Beta can finish the task in 18 days; Beta and Gama can do it in 24 days while Gama and Alpha can finish it in 36 days.

Calculation:

Time taken by (Alpha + Beta) to finish the work = 18 days

So, (Alpha + Beta)’s 1 day work = 1/18     ----(1)

Time taken by (Beta + Gama) to finish the task = 24 days

So, (Beta = Gama)’s 1 day work = 1/24     ----(2)

Time taken by (Gama + Alpha) to finish the work = 36 days

So, (Gama + Beta)’s 1 day work = 1/36      ----(3)

On adding eq. (1), (2) and (3), we have

2(Alpha + Beta + Gama)’s 1 day work = 1/18 + 1/24 + 1/36 = (4 + 3 + 2)/72 = 9/72 = 1/8

Also, (Alpha + Beta + Gama)’s 1 day work = 1/(2 × 8) = 1/16

So, Alpha, Beta, Gama together can make a sports car in 16 days.

Now, Alpha’s 1 day’s work = {(Alpha + Beta + Gama)’s 1 day’s work – (Beta + Gama)’s 1 day’s work} = 1/16 – 1/24 = (3 - 2)/48 = 1/48

Hence, Alpha alone can make the car in 48 days.

Beta 1 day’s work = {(Alpha + Beta + Gama)’s 1 day’s work – (Gama + Alpha)’s 1 day’s work}

= 1/16 – 1/36 = (9 - 4)/144 = 5/144

Hence, Beta alone can make the sports car in 144/5 days.

Gama’s 1 day’s work = {(Alpha + Beta + Gama)’s 1 day’s work – (Alpha + Beta)’s 1 day’s work}

= 1/16 – 1/18 = (9 - 8)/144 = 1/144

Hence, Gama alone can make the sports car in 144 days.

∴ Alpha, Beta and Gama alone can finish the task in 48 days, 144/5 days and 144 days respectively.

Related Questions

Each of the question below consists of a question and three statements number I, II and III given below it. You have to decide whether the data provided in the statement are sufficient to answer the question. If the bus is travelling from Surat to Ahmadabad and a car is travelling from Ahmadabad to Surat, then what is the distance between Surat and Ahmadabad? I. The speed of a car is 40% less than the speed of bus. Bus started at 9 am and car started at 10 am and they meet at 3 pm of the same day. II. After travelling for 1 hour, because of traffic average speed of bus is decreased by 20% and covers distance between Surat to Ahmadabad in 11 hours. Original speed of car is 20% less than original speed of bus and before crossing bus it covered 200 km if starts 1 hour later than bus. After crossing car, bus covers remaining distance in 5 hours. III. Speed of bus is 10 km/hr more than the speed of car and before crossing car ratio of distances covered bus and car in same time was 5 : 4. Time taken by car to cover the distance between Ahmadabad and Surat is 2 hours 15 minutes more than time taken by bus to cover the same distance.