Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone?
Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone? Correct Answer 12
Given,
Working together, if A, B, and C can finish a task in 4 days
However, after starting the task, B quits and A and C finish the remaining task in 6 days
Formula:
Total work = Efficiency × Time Taken
Calculation:
Total work = 12 units
Efficiency of A, B and C = 3 units/day
Efficiency of A and C = 2 units/day
Let efficiency of B be x,
⇒ x + 2 = 3
⇒ x = 3 – 2
⇒ x = 1 unit/day
∴ B alone can complete the whole work in = 12/1 = 12 days