K and L can complete a piece of work together in 15 days. K starts working and works for 10 days to complete two-fifth piece of work. L completes the remaining piece of work. The per-day wages paid to L  is Rs. 200. How much does L earn from completion of the remaining piece of work?

K and L can complete a piece of work together in 15 days. K starts working and works for 10 days to complete two-fifth piece of work. L completes the remaining piece of work. The per-day wages paid to L  is Rs. 200. How much does L earn from completion of the remaining piece of work? Correct Answer Rs. 4,500

Given:

K and L can complete a piece of work together in 15 days.

K starts working and works for 10 days to complete two-fifth piece of work.

L completes remaining piece of work.

The wages paid per day to L is Rs. 200.

Concepts used:

1 day work done by individual = Work/time

Time = Work/Efficiency

Total earnings = Wages per day × Number of working days

Calculation:

Time = Work/Efficiency

⇒ Time taken by K to complete full piece of work = 10 × 5/2 = 25 days

1 day work done by individual = Work/time

⇒ 1 day work of K = 1/25

Let L can complete the work in x days.

⇒ 1 day work of L = 1/x

K and L can complete a piece of work together in 15 days.

⇒ (1/25) + (1/x) = 1/15

⇒ 1/x = (1/15) – (1/25)

⇒ 1/x = 2/75

⇒ x = 75/2 days = 37.5 days

K completed 2/5th piece of work.

Remaining work = 1 – (2/5) = 3/5

Time taken by L to complete full work = 37.5 days

⇒ Time taken by L to complete 3/5 piece of work = (3/5) × 37.5 days = 22.5 days 

The wages paid per day to L is Rs. 200.

⇒ Total earnings of L = Rs. 200 × 22.5 = Rs. 4,500

∴ L earned Rs. 4,500 from completion of remaining 3/5th piece of work.

Related Questions

Each question below is followed by two statements I and II. You have to determine whether the data given in the statement is sufficient for answering the question. You should use the data and your knowledge of Mathematics to choose the best possible answer. P, Q and R together can complete a work in 12 days. All of them worked together for 6 days and then P left. How much time will Q and R together will take to complete the remaining work? I. If P completes a work in X number of days, then Q and R together complete the work in X number of days. II. After leaving the work, P completed another work in 10 days.