P, Q and R can do a work in 12 days, 15 days and 20 days respectively. They all started working together. If Q left after 2 days and R left 4 days before the completion of work, in how many days was the work completed?
P, Q and R can do a work in 12 days, 15 days and 20 days respectively. They all started working together. If Q left after 2 days and R left 4 days before the completion of work, in how many days was the work completed? Correct Answer 8 days
Given:
P can do the work = 12 days
Q can do the work = 15 days
R can do the work = 20 days
Concept:
Efficiency = Total work done/time taken
Calculation:
Let, the work was completed in = x days
According to the question,
⇒x/12 + 2/15 + (x – 4)/20 = 1
⇒ 8x – 4 = 60
⇒ 8x = 64
⇒ x = 8
∴ The work will be completed in 8 days