Sunny, nikki and rohan are working on their dream project after 4 days of working they had an argument. so that, sunny left the work. Remaining work is continued by nikki and rohan. Nikki left the work 2 days before its completion the project. In how many days work is completed if sunny, nikki and rohan separately complete the project in 15, 20 and 30 days respectively

Sunny, nikki and rohan are working on their dream project after 4 days of working they had an argument. so that, sunny left the work. Remaining work is continued by nikki and rohan. Nikki left the work 2 days before its completion the project. In how many days work is completed if sunny, nikki and rohan separately complete the project in 15, 20 and 30 days respectively Correct Answer 10

Given

Sunny, Nikki and Rohan separately complete the project in 15, 20 and 30 days respectively 

Concept used

Work = time × efficiency

Calculation 

LCM of 15, 20 and 30 = 60  i.e, total work = 60 units 

Efficiency of Sunny = 4 units / per day 

Efficiency of Nikki = 3 units / per day 

Efficiency of Rohan = 2 units / per day 

They altogether work for 4 days , so total work done in 4 days = 36 units 

Remaining work is completed by Nikki and Rohan but before 2 days of completion Nikki left work 

So, Rohan worked separately for 2 days  = 4 units 

Remaining work = 60 - 40 = 20 units 

This 20 units was done by Nikki and Rohan in = 20/5 = 4 days 

So, whole project was completed in = 4 + 2 + 4 = 10 days

∴ 10 days are required to complete the whole work.

Related Questions

Paddy transplantation in Punjab is a very hard labor-intensive back-breaking job. In the transplant season, teams of special people swarm the entire rural landscape employed by the farmers and can be seen laboring away in the fields under the hot sweltering sun. Farmer Jagtar Singh has a full-time help at his sprawling farm who goes by the name of Hari, and who hails from Allahabad, UP. During the paddy transplant season, it is up to Hari to rope in his brothers, sons, and cousins from his native village to complete the task well in time. All his people are skillful and masters of the trade and equally efficient at their jobs. So, this past season, this is how the work went. Hari started the work and after 't' hours was joined in by his brother Jaggi. After another 't' hours, Neelu, their cousin, also jumped into the fray. So, after every 't' hours, 1 person kept on joining the team of already working men, and this process kept on continuing till the completion of the work. The last person worked for 't' hours. In the last season, the very same men had completed the same work working 2 shifts of 12 hours all of them working simultaneously owing to some peculiar weather conditions and time constraints. Jagtar Singh is a fair and just paymaster which is why he faces no labor shortage at this crucial time and which is why the whole 'Hari clan' are more than happy to work for him and are at his beck and call. He pays each of them individually proportional to the work done by them. This time around, Hari received 11 times as much as Surinder, his eldest son, who was the last person to join in. In how much time was the work completed?