Arun can complete a piece of work in 15 days. Ritesh joined him after working for 3 days. If they complete the remaining work in 3 extra days, then in how many days Ritesh alone can complete the work?
Arun can complete a piece of work in 15 days. Ritesh joined him after working for 3 days. If they complete the remaining work in 3 extra days, then in how many days Ritesh alone can complete the work? Correct Answer 5
Given:
The Arun alone can complete the work = 15 days
Formula used:
W = E × T (Where, W = Work, E = Efficiency and T = Time)
Calculation:
Let be assume Ritesh alone can complete the work in R days
⇒ The efficiency of Arun = 1/15
⇒ The efficiency of Ritesh = 1/R
⇒ Remaining work after 3 days working of Arun = {1 - 3 × (1/15)}
⇒ 1 - 1/5 = 4/5
⇒ The efficiency of Arun and Ritesh = 1/15 + 1/R
⇒ The 4/5 work both can complete = 3 days
⇒ Both can complete the work = 3 × (5/4) = 15/4 days
⇒ 1/15 + 1/R = 4/15
⇒ 1/R = 4/15 - 1/15 = (4 - 1)/15 = 3/15 = 1/5
⇒ Ritesh alone can complete the work = 5 days
∴ The required result will be 5 days.