P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work? Correct Answer 15
Work done by P in 1 day = 1/20
Work done by Q in 1 day = 1/60
Work done P and Q in 1 day = 1/20 + 1/60 = 1/15
Work done by P and Q in 5 days = 5 ⨯ 1/15 = 1/3
∴ P and Q finished 1/3rd of the work in 5 days.
R finished 2/3rd of the work in 10 days
2/3 work = 10 days
1 work = 10 × (3/2) = 15 days
∴ R will finish the whole work in 15 days.