Find the total duration of the network of a construction project work shown in figure.

Find the total duration of the network of a construction project work shown in figure. Correct Answer 21 days

Explanation:

Important Points [ alt="F2 Chandramouli Madhuri 15.02.2022 D1" src="//storage.googleapis.com/tb-img/production/22/02/F2_Chandramouli_Madhuri_15.02.2022_D1.png" style="width: 416px; height: 437px;">

Related Questions

Statement (I): Crashing of project duration always increases the cost of the project on its completion, no matter what the indirect, or overhead, costs are. Statement (II): The critical path along the project activities network diagram is compressed in the process of investigating the crashing of the project duration, and not the non-critical activities, up to a certain stage of crashing.