The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. The critical duration for this construction project is
The activity-on-arrow network of activities for a construction project is shown in the figure. The durations (expressed in days) of the activities are mentioned below the arrows. The critical duration for this construction project is Correct Answer 15 days
Concept:
TiE = Early start time
TjE = Early Finish time
TiL = Latest start time
TjL = Latest Finish time -
tij = Duration of the activity
[ alt="13th May" src="//storage.googleapis.com/tb-img/production/20/05/13th%20May.png" style="width: 206px; height: 75px;">
TjE = TiE + tij
TjL = TiL + tij
Calculation:
[ alt="gate 2016 2 images Q39a" src="//storage.googleapis.com/tb-img/production/17/01/gate%202016_2_images_Q39a.PNG" style="height: 253px; width: 579px;">
The critical duration is 15 days which is observed along the path P – Q – T – W – X which is the critical path of the project.