A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is: Machine Jobs P Q R S T U M1 15 32 8 27 11 16 M2 6 19 13 20 14 7 The optimal make-span (in hours) of the shop is:
A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is: Machine Jobs P Q R S T U M1 15 32 8 27 11 16 M2 6 19 13 20 14 7 The optimal make-span (in hours) of the shop is: Correct Answer 115
According to Johnson’s algorithm sequencing of jobs is
|
R |
T |
S |
Q |
U |
P |
Now,
|
Job |
M1 |
M2 |
||
|
In |
Out |
In |
Out |
|
|
R |
0 |
8 |
8 |
21 |
|
T |
8 |
19 |
21 |
35 |
|
S |
19 |
46 |
46 |
66 |
|
Q |
46 |
78 |
78 |
97 |
|
U |
78 |
94 |
97 |
104 |
|
P |
94 |
109 |
109 |
115 |
From this the optimal make span of the shop is 115.