In normal circumstances where ambient temperature does not fall below 15°C, for a properly cured reinforced concrete slabs spanning up to 4.5 metre span cast using ordinary Portland cement, the props provide can be removed only after a minimum period of

In normal circumstances where ambient temperature does not fall below 15°C, for a properly cured reinforced concrete slabs spanning up to 4.5 metre span cast using ordinary Portland cement, the props provide can be removed only after a minimum period of Correct Answer <p>7 days</p>

In normal circumstances where ambient temperature does not fall below 15°C and where ordinary Portland cement is used and adequate curing is done, following striking period may be used

As per Clause 11.3.1 of IS:456-2000

Type of Formwork

Minimum Period Before Striking Formwork

Vertical formwork to columns, walls, beams.

16 - 24 h (1 Day)

Soffit formwork to slabs

3 days

Soffit formwork to beams

7 days

Props to slabs

a. Spanning up to 4.5 m

b. Spanning over 4.5 m

7 days

14 days

Props to beams and arches

a. Spanning up to 6 m

b. Spanning over 6 m

14 days

21 days