Select the correct alternative from the given choices. A, B and C can finish certain piece of work in 12 days, 15 days and 20 days respectively. A started working and is assisted by B and C on alternative days. This way, A, B and C finishes 85% of the total work. The remaining work is finished by D and the total number of days taken to finish the work is 9 days. Find the number of days C and D will take to finish half of this work when C works at 75% of his efficiency?
Select the correct alternative from the given choices. A, B and C can finish certain piece of work in 12 days, 15 days and 20 days respectively. A started working and is assisted by B and C on alternative days. This way, A, B and C finishes 85% of the total work. The remaining work is finished by D and the total number of days taken to finish the work is 9 days. Find the number of days C and D will take to finish half of this work when C works at 75% of his efficiency? Correct Answer 40 / 7
Let the total work be 60(LCM of 12, 15 and 20)
The amount of work A, B and C do in a day is 5, 4 and 3 units respectively.
⇒ A and B do 9 units of work in a day.
⇒ A and C do 8 units of work in a day.
Thus, 17 units of work is completed in two days.
⇒ 85% of the total work = (85 / 100) × 60 = 51
51 units of work will be completed in 3 × 2 = 6 days
Hence, D finished 9 units of work in 3 days.
⇒ D do 3 units of work in a day.
⇒ D will finish 60 units of work in 20 days.
When C works at 75% of his efficiency,
⇒ Efficiency of C = 3 / 4 × 3 = 2.25
Half of the work = 60 / 2 = 30 units
∴ Number of days taken by C and D to complete half of the work = 30 / (3 + 2.25) = 40 / 7 days