A work can be finished by 2 men in 7 days. The same work can be finished by three women in 4 days. The same work can be finished by 7 children in 3 days. Find the number of days taken to finish the entire work when 1 man, 1 woman and 1 child is working.
A work can be finished by 2 men in 7 days. The same work can be finished by three women in 4 days. The same work can be finished by 7 children in 3 days. Find the number of days taken to finish the entire work when 1 man, 1 woman and 1 child is working. Correct Answer 84 / 17
Given:
A work can be finished by 2 men in 7 days. The same work can be finished by three women in 4 days. The same work can be finished by 7 children in 3 days.
Concept Used:
If one man can finish a work in d days, his one-day’s work would be 1 / d.
Calculation:
⇒ 1 man finish the work in 14 days
⇒ 1 woman finish the work in 12 days
⇒ 1 child finish the work in 21 days
So, 1-day work of man, woman and child = 1/14 + 1/12 + 1/21 = 17/84
∴ The number of days taken to finish the entire work is 84/17 days.