4 men can finish work in 6 days, 8 women can finish the same work in 15 days, 10 children can finish the same work in 24 days. How long a team of 1 man, 2 women,and 2 children will take to finish the same work?
4 men can finish work in 6 days, 8 women can finish the same work in 15 days, 10 children can finish the same work in 24 days. How long a team of 1 man, 2 women,and 2 children will take to finish the same work? Correct Answer 15 days
Given:
4m = 6 days
8w = 15 days
10c = 24 days
Formula used:
Total work = Efficiency × days
Calculations:
⇒ 4m × 6 = 8w × 15 = 10c × 24
⇒ m = 5w = 10c
⇒ m : w : c = 10 : 2 : 1
⇒ Total work = 4m × 6 days
⇒ Total work = 4 × 10 × 6
⇒ Total work = 240
⇒ Efficiency of 1m, 2w and 2c = 1 × 10 + 2 × 2 + 2 × 1
⇒ Efficiency of 1m, 2w and 2c = 10 + 4 + 2
⇒ Efficiency of 1m, 2w and 2c = 16
⇒ Days = 240/16
⇒ Days = 15 days
∴ 1 man, 2 women and 2 children will take15 days to finish the work.