X did a task for 24 days and left in incomplete. He could have finished the task all by himself in a total of 36 days. Y, who can finish the task alone in 18 days, will take how many more days to complete the task?

X did a task for 24 days and left in incomplete. He could have finished the task all by himself in a total of 36 days. Y, who can finish the task alone in 18 days, will take how many more days to complete the task? Correct Answer 6

[ alt="F2 S.G 28.3.20 Pallavi D1" src="//storage.googleapis.com/tb-img/production/20/03/F2_S.G_28.3.20_Pallavi_D1.png" style="width: 160px; height: 81px;">

Total work = 36

Work done by X in 24 days = 1 × 24 = 24

Remaining work = 36 - 24 = 12

Remaining work, Y complete in = 12/2 = 6 days.